Start = the current start date = the Remaining Start date until started then = Actual Start date.

Finish = the current finish date = Planned Finish date until started then = Remaining Finish date while in progress then = Actual Finish date when completed.

Actual Start = date the activity started.

Actual Finish = date the activity actually finished.

Early Start = Remaining Start date. The earliest date the remaining work for the activity can begin. This date is based on activity relationships, schedule constraints, and resource availability.

Early Finish = Remaining Finish date. The earliest date the activity can finish. This date is based on activity relationships, schedule constraints, and resource availability.

Late Start = Remaining Late Start date. The latest date the remaining work for the activity must begin without delaying the project finish date. This date is based on activity relationships, schedule constraints, and resource availability.

Late Finish = Remaining Late Finish date. The latest date the remaining work for the activity must finish without delaying the project finish date. This date is based on activity relationships, schedule constraints, and resource availability.

Planned Start  = Early Start or a manual date (by user) until started then = Actual Start date

Planned Finish = Early Finish or a manual date (by user) until finished then = Actual Finish date.

Anticipated Start = The expected start date of the Project, EPS node, or WBS level, manually entered and not affected by scheduling. An anticipated start date cannot be entered at the activity level.

Anticipated Finish = The expected finish date of the Project, EPS node, or WBS level, manually entered and not affected by scheduling. An anticipated finish date cannot be entered at the activity level.

Remaining Start = Planned Start until started.. then = Data date..then upon completion = blank.

Remaining Finish = Planned Finish until started.. then upon completion = blank.

Remaining Late Start =  The latest date the remaining work for the activity must begin without delaying the project finish date. When the activity is complete, the Remaining Late Start is blank.

Remaining Late Finish =  The latest date the activity must finish without delaying the project finish date. When the activity is complete, the Remaining Late Finish is blank.

Expected Finish =  The date the activity is expected to finish, according to the primary resource. You may choose to use the Expected Finish dates or not.

Constraint Date = An imposed start or complete, primary and secondary constraints can be entered.

Suspend Date = The date on which an activity’s progress was, or is planned to be, suspended.

Resume Date = The date on which an activity’s progress was, or is planned to be, resumed.

 

An A appearing after the Start or Finish value indicates that the value is the Actual Start or Actual Finish.

An * appearing after the Start or Finish value indicates that there is a Start or Finish constraint on this activity.

What Our Clients Say

"Beth is absolutely wonderful to work with! I appreciate her patience and professionalism. It’s a relief to know I can count on her to respond and be a life line for us as we continue to learn the system. She is truly top notch."

Eastbound Mechanical

"I wanted to let you know Dan did a great job. He has a vast amount of knowledge, and I feel very fortunate to be working with him."

H.F. (Mechanical Contractor)

"We appreciate Tim and all of his excellent support."

M.J. (Manufacturing Firm)

"Kristen is a very valuable resource for us!"

LCI-Lineberger Construction Inc.

"I want to let you know how grateful we are for Robert Pacheco’s assistance. He was able to meet with me and discuss the issue promptly and complete the fix within a short amount of time. He is surely an asset, and we are thankful to have such a great resource."

Marques General Engineering, Inc.

"Greg is terrific, and I’m so excited to have a better resource! I have him working on several projects now with many more to come."

Progressive Plumbing

"Michael and Matthew have exceeded my needs and expectations. I get help same day 95% of the time, which is very important in my business at times. They are professional and courteous 100% of the time. Zero complaints."

Mitchell Brothers

"It’s a pleasure working with Robert. He's very patient, knowledgeable and goes far beyond to help with any issues we have as a company or as an individual."

HL Contractors

"The level of service CDP provides is exceptional and always far exceeded my expectations. You can quote me on that!"

The Wesson Group LLC

"He did a great job online and an equally great job in person. We’re enjoying working with our new Spectrum Viewpoint accounting software."

Chambliss & Rabil Contractors, Inc.

"Thank you for your assistance/responsiveness to assist us in getting P6 back online so quickly today. We appreciate all the support you provide."

M.J. (Manufacturing Firm)